DCK Exclusive: Infomart President John Sheputis Talks Strategy
In an interview with Data Center Knowledge, Infomart President John Sheputis talks strategy and discusses plans for 35 megawatts of development slated for 2017.
December 2, 2016
![Infomart Portland Infomart Portland](https://eu-images.contentstack.com/v3/assets/blt8eb3cdfc1fce5194/blt16aa1f5680c6e508/66210e4b28510e0d9a3d8ced/Link_20-_20DCK-Informart-Portland-Hillsboro-OR1_4.jpg?width=1280&auto=webp&quality=95&format=jpg&disable=upscale)
Infomart Data Centers primarily leases premium wholesale and colocation services to IT service providers, cloud hosting providers, content and social media companies. A major tenant in Dallas is connectivity giant Equinix, the largest publicly traded data center REIT.
These type of customers typically require concurrently maintainable data center services, and most notably, the standard Infomart service level agreement promises 100 percent uptime. President John Sheputis confirmed to Data Center Knowledge that the company has never had an SLA event.
Becoming a National Provider
Back in 2014, Fortune Data Centers and Dallas Infomart pooled their assets under the Infomart Data Centers flag, headed by Sheputis. Since both entities were owned by real estate funds controlled by ASB Capital Management, it eased the process of combining resources and talent.
Sheputis told Data Center Knowledge that around that same time that RFPs (customer requests for proposals), were increasingly focused on questions such as: Where else do you have facilities? Are you able to grow with us?
Read more: Merger Creates National Data Center Provider
The ability for Infomart to present four Tier 1 market options to tenants: Dallas, Silicon Valley, Portland, and Ashburn in 2017, has continued to grow in importance. Infomart currently operates 2.3 million square feet in its data center portfolio, with about 35MW in various stages of active development.
Infomart takes a pure wholesale approach to the data center business, and does not compete with its tenants. Infomart does not mark-up power, or share in savings negotiated with electric utilities. Notably, Infomart does not charge a monthly recurring fee for cross-connects, including the connectivity-focused iconic Dallas facility. This approach differentiates Infomart from other landlords, including most publicly traded peers. Here is a closer look at Infomart on a market by market basis.
Infomart Portland - LinkedIn
LinkedIn recently consolidated US data center operations by leasing 8MW of custom built data hall space from Infomart. This is the first LinkedIn data center designed to operate at a scale of 100,000-plus servers.
Read more: LinkedIn Adopting the Hyperscale Data Center Way
The availability of low-carbon hydroelectric power from Bonneville Power Administration certainly factored into the decision for LinkedIn to select the "Silicon Forest" of Hillsboro, near Portland, Oregon as a location for its new, high-density data center design.
Source: LinkedIn
However, a highly collaborative design-build approach between landlord and tenant played a major role in LinkedIn selecting Infomart Portland to be the home for its state-of-the-art LOR1 data center.
Sheputis and his Infomart team were able to roll up their sleeves to work with LinkedIn engineers to provide facility features such as the 415 volt electrical distribution system, a 400A Starline bus above the racks, and an efficient chiller plant delivering supply water at 67 degrees. These design elements support LinkedIn's hot/cold containment at the rack level utilizing rear door heat exchangers, allowing for flexible cabinet designs up to 24kW.
Read more: LinkedIn’s Award-Winning Hillsboro Data Center Goes Live
The Oregon climate allows LinkedIn to leverage "free cooling" from water side economization 60 percent of the year, which along with an overall energy efficient design, contributes to a PUE as low as 1.06. The Uptime Institute recently has recognized LinkedIn and Infomart Portland with their Efficient IT award. Notably, this was the first time the award was given in a multi-tenant data center where the user and landlord were different entities.
Infomart currently has 4 MW of move-in ready space and 8MW of shell available at the 24 MW Hillsboro property.
Infomart Ashburn
The former 180,000 square foot AOL data center in Sterling, VA was purchased by Infomart in 2014 with just 6MW of critical power. In most other ways the existing facility was state-of-the-art. Infomart is currently completing an upgrade of the entire mechanical and electrical infrastructure to bring this facility up to Tier III design standards with a PUE of 1.25 or better.
Sheputis told Data Center Knowledge that Infomart intends to leverage best practices learned from the LinkedIn collaboration in future facilities, including the former AOL site.
During the process of evaluation and design, Infomart decided it would be market savvy to increase the power density to support 300kW-400kW per square foot, or 15MW-20MW for the entire facility. This process has pushed out the opening of the Infomart Ashburn data center. However, the initial 6MW Phase 1 will commissioned, and a 2MW data hall will be completed and available by Q2 2017.
Silicon Valley - A Power Advantage
Mastering utility rate structures and creating power options has become a competitive advantage for Infomart in San Jose, California.
Sheputis explained that PG&E as a regulated California utility does not make a profit on producing and supplying energy. While at first blush it might appear counter-intuitive, PG&E actually makes money "from moving electricity through its transmission and distribution systems." Sheputis took advantage of a brief window in time to apply and be accepted into PG&E's Direct Access program.
Direct Access allows Infomart to purchase electricity at an agreed upon rate from third-party Energy Service Providers. The electrons are the same, but are delivered and consumed at a lower total cost for power. Sheputis gleaned insights into free markets and deregulation during his stint in the mid-to-late 1990s with Enron Energy Services and Enron Wholesale. Choice of electrical suppliers also allows customers more flexibility when it comes to reducing facility carbon footprints through purchasing renewable energy, even if the tariff is a bit higher.
Infomart can offer data center customers a slightly lower rate structure in San Jose, than the current tariff being charged by Santa Clara Power. SCP is generally viewed to be the low-cost provider for Silicon Valley data center operators.
Infomart has 3 MW move-in ready space available at the existing 9.3 MW Silicon Valley property with a PUE of 1.3. Additionally, the redevelopment of a 55,000 square foot building will provide another 6MW of data center capacity and 10,000 of private office at this site.
Infomart Dallas - Leveraging Connectivity
The iconic Dallas Infomart contains 1.6 million square feet of data halls and support space, and over 100MW of critical power. Sheputis explained that Infomart only operates 30MW of that capacity, with the balance leased to major tenants such as Equinix who are responsible for their own footprint, including operating their own generators.
Read more: First Wholesale Data Center Suite Opens at Dallas Infomart
Infomart has a multi-phase expansion underway in Dallas. The first phase is building out unoccupied suites within the existing envelope. Infomart has initially developed the first 3MW, with 500kW underway (to be delivered in Feb 2017). There are another 7MW of requirements that Infomart has identified to be the next projects.
Phase 2 of the expansion would be 30MW, and require constructing a separate 300,000 square foot building on the property.
Ownership Matters - Patient Capital
Infomart Data Centers is owned by ASB Allegiance Real Estate Fund, a $6.6 billion real estate investment trust (REIT), which manages institutional capital.
Source: asbrealestate.com
Sheputis explained, that developers and private equity funds are looking for much higher returns than pension funds and life insurance companies, who he joked were "financial apex predators." They are often the natural long-term home for capital intensive assets such as data centers.
ASB is fairly patient capital. According to the Infomart website: "Ownership with the capital to support a long-term investment strategy means we can focus on providing our customers with the best products and services possible without the pressure to cut costs and boost ROI. It also means we have long-term financial stability and the agility to keep up with technological advances."
During 2017, the Infomart team has plenty of development projects and leasing opportunities in all four existing markets. However, Sheputis acknowledged that looking to 2018 and beyond, Infomart could be coming up on a strategic crossroads. Decisions will be made regarding expansions into other markets, growth by acquisition, or other strategic alternatives for Infomart.
Essentially, ASB and the Infomart management team will have to decide whether to expand and stay the course, merge privately, or look toward Wall Street for other alternatives.